Avenue Gardens Major Works (project W103)

Current status

Project status 1
Initial planning

Deciding the scope of the works

Project status 2
Project design and approval

Finalising the project specification, budget and programme

Project status 3
Onsite
Work starts: 07/07/2022
Work ends: 31/01/2024
Project status 4
Completion

End of works and the defects period 

Project update

Coffee Evening
Date: Wednesday 24 April
Time: 6pm to 7pm 
Location: St. Judes Community Hall, 71 Ilbert St., London W10 4QH
 

Scaffolding in the week (if applicable)

  • Holly House – scaffold striking
  • Fir House – scaffold striking

Works started in the week

  • Commencement of fabric repairs to Elm House
  • Commencement of fabric repairs to Ash House
  • Continuation of roof renewal to Ash House
  • Continuation of communal decorations to Elm House
  • Continuation of communal decorations to Ash House
  • Continuation of bin store door installations within Avenue Gardens (trimming/mastic application)
  • Cat Ladder installation’s to multiple blocks
  • PV installation to Elm House.
  • Hand rail installation to Elm House.

Works completed in the week

  • Site clearance of rear of pine house
  • Asbestos removal of SVP’s to ASH house
  • Fabric repairs to ELM HOUSE
  • New slates and lead aprons installed to roadside of Ash and Elm house
  • PV installation to ELM house 70% Complete
  • Handrail to ELM house complete
  • Liquid balconies completed;
    • 10 holly house – front and back
    • 11 Elm house – secondary balcony
    • 30 & 31 Ash House – liquid box gutter
    • 30 Ash house – secondary balcony 
    • 7 Ash house – secondary balcony 

4 Weeks Look Ahead

  • Scaffold strike to Fir and Holly in a progressive Manner.
  • Completion of installation of CAT ladder to Pine House
  • Completion of installation of CAT ladder to Fir House
  • Completion of installation of PV panels to Elm House
  • Completion of installation of PV panels to Ash House
  • Completion of installation of safety handrail system to Elm House
  • Completion of installation of safety handrail system to Ash House
  • Window overhauls within Avenue Gardens ongoing
  • Extractor fan replacements ongoing/subsequent making good works ongoing

Projected End Date

  • 6th June 2024 – Pending EOT acceptance

Contact United Living

Your dedicated Site Manager Charlie is here to support you and is your best point of contact.

During the work he will make sure that your home is being respected and will keep you well informed. You can contact Charlie on 07803 234783 or email [email protected]


 

 

 

 