Barrow Hill Landscaping and Car Park works (project Y140)

Current status

Project status 1
Initial Planning

Deciding the scope of works. 

Project status 2
Project Design and Approval

Finalising the project specification, budget and programme

Project status 3
On Site
Work starts: 02/09/2024
Work ends: 06/03/2025
Project status 4
Completion

End of works and defects period.

Project update

Meeting took place on the 15 January 2024 at the Barrow Hill village club with residents and United Living. Minutes of the meeting can be found in the documents section of this webpage.

Work started on site in September 2024. This followed an earlier consultation with residents to see if they wanted us to start work in June or September. Starting in September allowed residents to enjoy the amenities over the summer period. 

Published: 18 January 2024

Last updated: 29 November 2024