Avenue Gardens Major Works (project W103)

Current status

Project status 1
Initial planning

Deciding the scope of the works

Project status 2
Project design and approval

Finalising the project specification, budget and programme

Project status 3
Onsite
Work starts: 07/07/2022
Work ends: 30/11/2024
Project status 4
Completion

End of works and the defects period 

Project update

 

Projected End Date

  • November 2024 

Final Snagging Works
* All blocks will have a uniform stair nosings. This will be completed by October 2024. 

* Landscaping  

 

Drop-in Session

Date: 16/10/24

Morning: 10am - 1pm 

Afternoon/Evening: 4pm - 7pm

Location: St. Judes Community Hall, Ilbert Street 67, London W10 4QL

 

Contact United Living

Your dedicated Resident Liaison Officer, Thomas Kyrmishi, is here to support you and is your best point of contact. You can contact Thomas on 07909 368 600 or email [email protected]

 