Skip to main content

108 - 132 Westbourne Terrace Fire Safety Works (project V109)

Current status

Project status 1
Initial planning

Deciding the scope of the works. 

Project status 2
Detailed design and approval

Finalising the project specification, budget and programme.

Project status 3
Onsite
Work starts: 05/01/2023
Work ends: 22/08/2023
Project status 4
Completion

End of works and the defects period. 

Project update

This project is now complete.

This project started in January 2023 and finished at the end of August 2023. There was a small overrun of nearly one month in this project and we are grateful for resident's patience.

We will need Building Control approval for these works, after which the project will move into the 'defects period'.  

Published: 4 March 2021

Last updated: 12 August 2024