Current status
Project status
1
Initial planning
Deciding the scope of the works.
Project status
2
Detailed design and approval
Finalising the project specification, budget and programme.
Project status
3
Project status
4
Completion
End of works and the defects period.
Project update
This project is now complete.
This project started in January 2023 and finished at the end of August 2023. There was a small overrun of nearly one month in this project and we are grateful for resident's patience.
We will need Building Control approval for these works, after which the project will move into the 'defects period'.
Published: 4 March 2021
Last updated: 12 August 2024