Pimlico timeline
This programme is accurate as at 01 June 2009
Start date/early works: 17 December 2007
End date/project complete: 9 February 2011
Scope of Works
December 2008-April 2008
Phase 0 - Enabling Works
April 2008-July 2009
Phase 1 - South East Building Construction to include:
- Sports hall, fitness suite and changing areas
- Graphics
- Art
- Modern Foreign Languages
- ICT Areas for Design Technology
- Science.
April 2008-July 2009
Phase 2 - South West Building Construction to include:
- Kitchen and dining area
- Areas for Design & Technology
- Science
- Humanities Activity hall.
April 2009-August 2010
Phase 3 - North West and North East Building Construction to include:
- Public Library and Adult Education areas
- Offices
- Drama
- Maths
- Music
- English
- Post 16 Art
- additional Humanities.
September 2009-August 2010
Phase 4 - Activity Hall Construction
September 2010 - February 2011
Phase 5 - Remaining External Works to include:
- Removal of remaining temporary accommodation
- Final demolitions
- Hard play and games court
- Roadworks
- landscaping
- new Multi-Use Games Area.
Formal Handover: 9 February 2011