Pimlico timeline

This programme is accurate as at 01 June 2009

Start date/early works: 17 December 2007

End date/project complete: 9 February 2011

Scope of Works



December 2008-April 2008


Phase 0 - Enabling Works

April 2008-July 2009

Phase 1
- South East Building Construction to include:

  • Sports hall, fitness suite and changing areas
  • Graphics
  • Art
  • Modern Foreign Languages
  • ICT Areas for Design Technology
  • Science.

April 2008-July 2009

Phase 2 - South West Building Construction to include:

  • Kitchen and dining area
  •  Areas for Design & Technology
  • Science
  • Humanities Activity hall.

April 2009-August 2010

Phase 3 - North West and North East Building Construction to include:

  • Public Library and Adult Education areas
  • Offices
  • Drama
  • Maths
  • Music
  • English
  • Post 16 Art
  • additional Humanities.

September 2009-August 2010

Phase 4 - Activity Hall Construction

September 2010 - February 2011

Phase 5 - Remaining External Works to include:

  • Removal of remaining temporary accommodation
  • Final demolitions
  • Hard play and games court
  • Roadworks
  • landscaping
  • new Multi-Use Games Area.

Formal Handover: 9 February 2011