Westminster City School

This programme is accurate as at 11 March 2008
Start date/early works: 3 January 2008
End date/project complete: 19 August 2010

Scope of Works
03.01.08 - 03.01.10
Phase 0
Enabling Works
Work starts on site to prepare for construction programme including installation of some temporary accommodation and decant to Westminster Kingsway College

29.05.08 - 02.09.09
Phase 1a – 1c to include:
Construction of new building including basement, sports hall and activities
Other excavating includes new sixth form study areas, music, drama and ICT specialist areas and administration

23.07.09 - 05.01.10
Phase 2 to include:

Refurbish Block A Ground Floor
Refurbish existing music and sports block
Convert to Art and Religion studies

19.08.10 - 22.12.09
Phase 3 – to include:
Refurbish Block A 2 Floor Removal of temporary accommodation on First Floor
External works (multi use ground area)

Formal Handover (project completion): 19.08.10