This programme is accurate as at 27 March 2008
Start date/early works: 15 January 2008
End date/project complete: 31 August 2010
Scope of Works
11.01.08 – 04.07.08
Phase 0 – Enabling Works
Work starts on site to prepare for construction programme including:
Asbestos removal
Installation of temporary playground for St Vincent’s primary school
A new emergency exit and staircase installed at St. Vincent’s primary school
Some preparatory demolition at Blandford St
07.04.08 - 17.11.09
Blandford St - Phase 1 – New Building Construction to include:
Demolition of current building
Excavation and creation of foundations
Handover and decant to new building
24.04.09 - 23.07.09
Blandford St - Phase 2
Remodel of lower ground level and ground level for Foundation Stage unit
Refurbishment of 2nd and 4th floors for St Marylebone School
01.07.09 - 07.09.08
High St – Phase 1 to 3 (Block A 1st to 3rd floors) to include:
Asbestos removal
Services disconnection, preparation and protection Refurbishment of English and ICT rooms
Testing and Commissioning of furniture, fittings and equipment
01.07.08 – 02.09.08
High St – Phase 4 (Block B ground floor)
Sports Hall and Offices Block B – Risers
06.04.09 – 04.09.09
High St – Phase 5 (Block C) Plant Rooms
Asbestos removal
Services disconnection, preparation and protection
New equipment installation (if any)
06.09.09 – 07.09.09
High St – Phases 6 and 7 (Block C 2nd and 3rd floor) Services disconnection, preparation and protection Refurbishment of Science rooms
22.07.09 – 07.09.09
High St – Phase 8 (Block B 2nd and 3rd Floor)
Services disconnection, preparation and protection Refurbishment of rooms
23.07.08 – 23.05.10
High St – Phases 9 and 10 (Block C lower ground floor and ground floor)
Decant from Design Technology
24.05.10 – 22.12.10
High St – Phase 11 (Block A Lower Ground Floor and Ground Floor)
Services disconnection, preparation and protection Refurbishment of rooms
15.05.10 – 31.08.10
High St – Phase 12 (Block C 1st floor)
FF&E installation
Refurbishment of General Teaching rooms
22.07.10 – 31.08.10
High Street - Phase 13 (External Works)
Tarmac resurfacing
Curriculum Moves and Continuity
September 2008
Completely new ICT suite installed over the school holiday period at High St
September 09 onwards
Science rooms refurbished in sequence always leaving at least four labs available
November 09
Design and Technology moves from High St to Blandford St to all new rooms
November 09 onwards
Former technology rooms High St converted into refurbished Mathematics suite